SECTION 5: WALL ASSEMBLY
IMPORTANT: IF YOUR POOL HAS STEPS, REFER TO SECTION 18 FOR STEP LOCATION.
STEP 1: THE POOL WALLS ARE LOCATED AROUND THE STAKES OUTLINED PREVIOUSLY. SEE FIGURE 3. THE WALLS ARE ASSEMBLED IN THE SEQUENCE SHOWN IN FIGURE 7. THE DIAGONAL PANELS AT THE CORNERS OF THE
POOL HAVE THE HOLES FOR THE SKIMMER AND RETURN FITTINGS. CONSIDER VARIOUS CORNER PANEL LOCATIONS, WHICH WILL PROVIDE MAXIMUM CIRCULATION FOR YOUR POOL.
WHEN YOU DETERMINED THE LOCATION OF ALL THE PANELS, PLACE THE PANELS INTO THE EXCAVATION NEAR THEIR RESPECTIVE LOCATIONS.
WE SUGGEST AT THIS TIME TO DRAW A CHALK LINE ON THE FACE OF EACH PANEL EXACTLY 2 l/2" UP FROM THE BOTTOM ACROSS THE ENTIRE PANEL. THIS WILL ASSIST YOU WHEN YOU ARE PUTTING THE BASE IN THE POOL.
CHECK THE STRING THAT IS AROUND THE REE-BAR TO BE SURE IT IS TIGHT AND WAS NOT KNOCKED OFF DURING EXCAVATION. SEE FIGURE 3.
THE PANEL ASSEMBLY MUST START AT A CORNER. BOLT A SIDE PANEL TO THE CORNER PANEL USING FIVE (5) EACH 3/8"-16 x l" S.S. HEX HEAD CAP SCREWS. 3/8"-16 S.S. HEX NUTS. AND TWO (2) 3/8" ALUMINUM FLAT WASHERS. BOLT THE LONG END PANEL TO THE OTHER SIDE OF THE CORNER PANEL.
NOTE: THE PANELS MUST HAVE THE LINER BEAD RECEIVER ON TOP OF THE PANEL. SEE FIGURE 8. INSTALL THE OTHER CORNER PANEL ONTO THE END PANEL USING FIVE (5) 3/8"-16 x1” S.S. HEX HEAD CAP SCREWS, 3/8'-16 S.S. HEX NUTS, AND TWO (2) 3/8" ALUMINUM FLAT WASHERS. CONTINUE ASSEMBLING THE PANELS DOWN THE LONG SIDE OF THE POOL. PLACE THE BOLTS IN THE HOLES AS INDICATED IN FIGURE 9.
|